Evaluation Of Implementation Strategies And Methods To Improve Efficiency In The Bagong Main Dam Project Trenggalek

Authors

  • moch. khamim State Polytechnic of Malang
  • Mohamad Zenurianto State Polytechnic of Malang
  • Raden Ajeng Mariyana State Polytechnic of Malang
  • Roland Gasenda Suryaningrat State Polytechnic of Malang

DOI:

https://doi.org/10.51278/ajse.v4i2.2030

Abstract

Earthfill dam construction requires effective strategies to ensure structural safety, construction quality, and efficient use of time and resources. This study examines the construction strategy and implementation method of the Main Dam of the Bagong Dam Project, Indonesia, which is designed as a vertically zoned earthfill embankment with a length of 620 m, a crest width of 12 m, a crest elevation of +330 m, and a height of 82 m. The research focuses on the application of a zoning-based construction approach to improve construction efficiency under complex field condition. The results indicate that dividing the embankment into six functional zones enables systematic layer-by-layer construction and parallel work execution, resulting in a planned construction duration of 937 working days. The integration of material zoning, quality control procedures, and optimized equipment management ensured that all embankment layers achieved more than 95% of maximum dry density. Coordinated equipment utilization further improved productivity, allowing approximately 304,653 m³ of embankment work to be completed within 53 working days during critical construction stages. In addition, the implementation of a structured safety management system supported the achievement of zero-accident construction performance. These findings demonstrate that the integration of zoning strategy, systematic construction sequencing, quality management, equipment planning, and safety control significantly enhances time and cost efficiency while maintaining construction quality. The proposed approach provides a practical framework for earthfill dam construction projects in Indonesia and other regions with similar geological and climatic conditions.

References

Dillon, A., & Fishman, R. (2019). Dams: Effects of hydrological infrastructure on development. Annual Review of Resource Economics, 11(1), 125–148

https://doi.org/10.1146/annurev-resource-100518-093913

Galindo, R., Sánchez-Martín, J., & Olalla Marañón, C. (2020). Sustainable construction of earth dams using heterogeneous materials from the dam site. Sustainability, 12(23), 9940.

https://doi.org/10.3390/su12239940

Nugraha, A. S., & Putranto, L. S. (2019). The effect of heavy equipment management on construction project and company performance. IOP Conference Series: Materials Science and Engineering, 650(1), 012019.

https://doi.org/10.1088/1757-899x/650/1/012019

Liu, Y., Gan, Y., Yang, Z., & Qiang, S. (2025). Intelligent construction technology for reservoir dams. Automation in Construction, 175, 106177. https://doi.org/10.1016/j.autcon.2025.106177

Zhang, L., Wu, X., & Skibniewski, M. J. (2021). Risk-based planning and scheduling of heavy equipment operations in large-scale construction projects. Journal of Construction Engineering and Management, 147(4), 04021019.

https://doi.org/10.1061/(ASCE)CO.1943-7862.0002034

Kim, J., Lee, H., & Park, M. (2020). Equipment productivity optimization for earthwork operations considering time–cost trade-offs. Automation in Construction, 118, 103293.

https://doi.org/10.1016/j.autcon.2020.103293

Al Basar, M. H., Khamim, M., & Utoyo, S. (2021). Main dam project planning for the Bendo Dam development in Ponorogo Regency. Jurnal Online Skripsi Manajemen Rekayasa Konstruksi, 2(3), 292-297.

https://doi.org/10.55404/jos-mrk.2021.02.03.292-297

Yudha, A. R., Utoyo, S., & Purnomo, F. (2022). Feasibility study of the Bagong Dam development in Trenggalek Regency. Jurnal Online Skripsi Manajemen Rekayasa Konstruksi, 3(4), 241-245.

Baskhara, H. N., & Riskijah, S. S. (2023). Application of value engineering in the construction of the Bagong Dam main dam. Jurnal Online Skripsi Manajemen Rekayasa Konstruksi, 4(1), 154-159.

Downloads

Published

2025-12-31

How to Cite

khamim, moch., Zenurianto, M., Ajeng Mariyana, R., & Gasenda Suryaningrat, R. (2025). Evaluation Of Implementation Strategies And Methods To Improve Efficiency In The Bagong Main Dam Project Trenggalek. Asian Journal Science and Engineering, 4(2), 148–160. https://doi.org/10.51278/ajse.v4i2.2030